EirGrid Report Identifies Route Corridor Options for the Grid Link Project New Power Line to Facilitate Job Creation and Investment in the South and East Tuesday 3rd September 2013:
EirGrid published a significant report on the Grid Link Project identifying a number of feasible 1km wide route corridor options for a new 400kV overhead power line linking Leinster and Munster.
The Grid Link Project Lead Consultant�s Stage 1 Report Prepared for EirGrid by RPS Group
The purpose of this Lead Consultant�s Stage 1 Report is to draw together the work completed as part of Stage 1 of EirGrid�s
Project Development Road Map for the Grid Link Project.
The Grid Link Project Consultation Report No.2 Prepared for EirGrid by RPS Group
This report sets out the process for the second round of public consultation for the Grid Link Project.
The Grid Link Project User�s Guide to the Constraints Report
This document provides a description of the Constraints Report and a guide to accessing the
constraints maps.
The Grid Link Project User�s Guide to the Constraints Report
This document provides a description of the Constraints Report and a guide to accessing the
constraints maps.
THE GRID LINK PROJECT Floodplains (Map 1 of 4)
A3 THE GRID LINK PROJECT Floodplains (Map 1 of 4) AT SCALE 1:300,000
THE GRID LINK PROJECT High Pressure Sites map
A3 THE GRID LINK PROJECT High Pressure Sites map AT SCALE 1:610,000
THE GRID LINK PROJECT High Status Sites map
A3 THE GRID LINK PROJECT High Status Sites map AT SCALE 1:610,000
THE GRID LINK PROJECT Groundwater Status map
A3 THE GRID LINK PROJECT Groundwater Status map AT SCALE 1:610,000
THE GRID LINK PROJECT Surface Water Status (Chemical) Map
A3 THE GRID LINK PROJECT Surface Water Status (Chemical) Map AT SCALE 1:610,000