Kildare Dublin Grid Reinforcement Project Update April 2026
The existing electricity infrastructure in the East Kildare and South Dublin area is at risk of reaching its capacity limit. To address this need, new infrastructure is required to ensure a reliable, sustainable electricity supply to communities, residents, schools and businesses.
Tionscadal Treisithe Eangaí Cill Dara Baile Átha Cliath: An Nuacht is Déanaí maidir leis an Tionscadal, Márta 2026
Tá an bonneagar leictreachais atá i gceantar Chill Dara Thoir agus Bhaile Átha Cliath Theas i mbaol teorainn a thoillte a bhaint amach. Chun aghaidh a thabhairt ar an riachtanas seo, tá gá le bonneagar nua chun soláthar leictreachais iontaofa, inbhuanaithe chuig pobail, cónaitheoirí, scoileanna agus gnólachtaí a chinntiú
Kildare Dublin Project: Hynestown to Steelstown Emerging Best Performing Technology Option Report
This Emerging Best Performing Technology Option Report provides an update on the progress of the new Steelstown Substation and new Hynestown-Steelstown Circuit. The report documents the decision for the substation technology and identifies the emerging best performing option for the circuit technology.
Kildare Dublin Project: Hynestown to Maynooth Emerging Best Performing Technology Option Report
This Emerging Best Performing Technology Option Report provides an update on the progress of the new Hynestown Substation and new Hynestown-Maynooth Circuit. The report documents the decision for the substation technology and identifies the emerging best performing option for the circuit technology.
Amach ón gCósta a Chumhachtú An Cósta Theas - An Nuacht is Déanaí maidir leis an Tionscadal, Márta 2026
Is ionann Amach ón gCósta a Chumhachtú – An Cósta Theas agus clár EirGrid lena dtógfar an bonneagar is gá don eangach nua tharchurtha chun cumhacht a ghinfear sna feirmeacha gaoithe amach ón gcósta theas a thabhairt isteach inár n-eangach náisiúnta.
Powering Up Offshore South Coast - Project Update, March 2026
Powering Up Offshore – South Coast is EirGrid’s programme to build the new transmission grid infrastructure needed to bring the power generated by offshore windfarms on the south coast into our national grid. This update provides the latest news on the project.
East-West Interconnector - Asset Management Policy
This asset management policy provides the framework for setting asset management objectives which support the delivery of EirGrid organisational objectives. It also provides the framework within which stakeholder needs and expectations will be determined. To assure the asset is best utilised over its life cycle in terms of performance, cost and risk, an asset management system will be implemented and certified to the international standard for asset management, ISO 55001 Asset Management -Management System - Requirements.
Powering Up the North West: Step 3 Engagement and Consultation Report
This report summarises the engagement and consultation activities undertaken during Step 3 of EirGrid’s 6- Step approach, which focuses on “What is the best option and what area might be affected?”. This step in the process included public information events, stakeholder engagement, and feedback analysis. The insights gathered will inform the next phase of the project: Step 4 “Where Exactly Should We Build”
Celtic Interconnector Newsletter Issue 9 - December 2025
The trenching and installation of ducting to carry the high voltage direct current (HVDC) cable on the route from Claycastle Beach to the converter station in Ballyadam is complete. Over 60% of the HVDC cables have been installed. Cable installation and jointing of the cables on the N25 between Youghal and Killeagh and between Killeagh and Castlemartyr has been completed. Permanent road reinstatement on these sections has finished. At the landfall, the cofferdam was removed and the beach returned to its former state for public use.