Northern Ireland Authority For Energy Regulation (NIAER) Letter to Leslie Byrans
Northern Ireland Authority For Energy Regulation (NIAER) Letter to Leslie Byrans
Re: Capacity Of Additional North- South Interconnector 9th March 2006 Ref:26341
Re: Capacity Of Additional North- South Interconnector 9th March 2006 Ref:26341 Letter from Denis Cagney Director Energy Networks to Andrew Cooke
Confidential Additional Electricity Interconnection between Northern Ireland and Republic of Ireland
Confidential Additional Electricity Interconnection between Northern Ireland and Republic of Ireland
North-South 400kV Interconnection Development Project Activity - 2005
North-South 400kV Interconnection Development Project Activity - 2005
ADDITIONAL INTERCONNECTION BETWEEN NORTHERN IRELAND AND REPUBLIC OF IRELAND TECHNICAL REPORT - PART 1 � STUDIES APRIL 2001 TO JULY 2004
A suite of technical studies were undertaken jointly by a team of engineers from ESBNG and
NIE over the period April 2001 to July 2004. The presentation of the results from these
studies is provided in this report. The purpose of the technical study work is to quantify the
improvement in transmission capacity and system security that would be provided by each of
the interconnection options.
North-South 400kV Interconnection Development Project Activity – 2004
North-South 400kV Interconnection Development Project Activity – 2004
North-South 400kV Interconnection Development Project Activity – 2002
North-South 400kV Interconnection Development Project Activity – 2002