Grid West Electricity Transmission Scheme Study Area Rationale Memorandum Prepared for EirGrid by TOBIN Consulting Engineers
This Memorandum aims to provide a considered view of the appropriate boundaries of a study area for
corridor and route selection between three end nodes of the eventual Grid West development proposal
(a �node� refers to an area within which the end connection will be located).
NOTICE OF DIRECT PLANNING APPLICATION TO AN BORD PLEAN�LA IN RESPECT OF A STRATEGIC INFRASTRUCTURE DEVELOPMENT Co. Cork
NOTICE OF DIRECT PLANNING APPLICATION TO AN BORD PLEAN�LA IN RESPECT OF A STRATEGIC INFRASTRUCTURE DEVELOPMENT Co. Cork
MAJOR NEW ELECTRICITY POWER LINK FOR LEINSTER & MUNSTER TO ENSURE A SECURE AND RELIABLE ELECTRICITY SUPPLY, PROVIDE A PLATFORM FOR ECONOMIC GROWTH AND SUPPORT SUSTAINABLE & CLEAN ENERGY PUBLIC CONSULTATION OPENS TODAY
Cork, 12TH April 2012: Public consultation starts on the Grid Link Project, an estimated �500 million project planned by EirGrid to upgrade the electricity grid that will deliver a wide range of benefits to the national and regional economies. The development will involve the construction of a new power line linking Leinster and Munster.
GRID25 NEWSLETTER Issue No 7. April 2012
This Newsletter covers GRID25 PROGRAMME MILESTONES ACHIEVED to date April 2012
The Grid Link Project Prepared for EirGrid by RPS Group Study Area Paper
This paper has been prepared by RPS Group on behalf of EirGrid. The intention of this paper is to
outline the proposed study area for the project and record the relevant considerations and
deliberations on the path to defining the study area. The proposed study area presented at the end of
this paper will form the basis of public consultation and the submissions received during this
consultation process together with the other considerations outlined in this paper will inform the final
project study area brought forward.
Presentation to Monaghan County Council - North-South Project
Presentation to Monaghan County Council - North-South Project
West Galway 110/38kV substation Review of Environmental Constraints
The purpose of this report is to provide baseline environmental information in relation to a number of possible locations where the substation could be located and to provide an indication of potential environmental impacts associated with the various options considered.
Tionscadal Fhost�isi�n Leictreachais 110 / 38 kV na Gaillimhe Thiar C�im 1 Doicim�ad Nuashonraithe Tionscadail
Tionscadal Fhost�isi�n Leictreachais 110 / 38 kV na Gaillimhe Thiar C�im 1 Doicim�ad Nuashonraithe Tionscadail
West Galway 110/38 kV Electricity Substation Project Stage 1 Project Briefing Document
West Galway 110/38 kV Electricity Substation Project Stage 1 Project Briefing Document
West Galway 110/38 kV Substation STAGE 1 LEAD CONSULTANT�S REPORT IDENTIFICATION OF LEAST CONSTRAINED SITES February 2012
EirGrid proposes to develop a new 110/38 kV electricity substation west of Moycullen,
County Galway, at a location along the permitted Salthill � Screebe 110 kV overhead line
(OHL). ESB International (ESBI) has been appointed by EirGrid as the Lead Consultant for
this project.