North South 400 kV Interconnection Development Preliminary Re-evaluation Report May 2011

This review includes (but is not restricted to) the specific subject matter of that
application for approval, the Environmental Impact Statement (and supporting studies) accompanying
the application, alternatives considered, and third party and other submissions made to An Bord
Plean�la. This also includes information provided to, or obtained by EirGrid, subsequent to the
withdrawal of that previous application. This is in order to ascertain whether the scope, content,

LAOIS � KILKENNY REINFORCEMENT PROJECT: Assessment of Alternative 400/110kV Substation Study Areas

This report details the findings of a study carried out by ESBI on behalf of EirGrid in order to
assess the suitability of potential 400/110kV substation study areas for the Laois-Kilkenny
Reinforcement Project.

Dublin North Fringe 220 kV Reinforcement Project Functional Parameters for Site Selection April 18, 2011

This report sets out the technical requirements and corresponding functional parameters
used to identify a study area for the new Dublin North Fringe 220 kV bulk supply point
(BSP) planned for Dublin North Fringe area.