Cavan Post � statement
EirGrid Statement On PB Power Report-Cavan Post
Report reveals overhead lines more suitable technology for North East power projects Thursday 12 February 2009
A study conducted by independent experts has confirmed overhead power lines are the
cheapest and most secure option for the planned power lines in the north east.
report reveals overhead lines more suitable technology for North East power projects
A STUDY conducted by independent experts has confirmed overhead power lines are the cheapest and most secure option for the planned power lines in the north east.
Non-Technical Summary February 2009 Cavan - Tyrone And Meath - Cavan 400kV Power Lines Comparison of High Voltage Transmission Options Non-Technical Summary
This is a non-technical summary of the Parsons Brinckerhoff
(PB Power) Comparison of High Voltage Transmission Options
Report (the Report).
CAVAN-TYRONE AND MEATH-CAVAN 400KV TRANSMISSION CIRCUITS COMPARISON OF HIGH VOLTAGE TRANSMISSION OPTIONS: ALTERNATING CURRENT OVERHEAD AND UNDERGROUND, AND DIRECT CURRENT UNDERGROUND FINAL REPORT
This report seeks to establish the feasibility of alternative underground technologies by making technical, environmental and cost comparisons between them and the proposed OHL Project.
Cavan to Tyrone 400kV overhead Powerline Project Distribution of Whooper Swan Feeding and Roosting Sites
The aim of this study was to determine the numbers and distribution of Whooper Swans within a study
area that includes the route corridor options for the proposed Cavan to Tyrone 400kV overhead
powerline. This study is ongoing to coincide with the season when Whooper Swans are present in
Ireland and will continue until April 2009 which forms part of Wintering Survey Period 2.
110kV Lines General Outline Drawing For Planning Application Tower Type 149E, 12, 15 & 18 Metre Towers (0-90deg) Earthwire
A0 110kV Lines General Outline Drawing For Planning Application Tower Type 149E, 12, 15 & 18 Metre Towers (0-90deg) Earthwire AT SCALE 1:100
Outline Drawing of 110kV Braced Wood Pole Set (Shield Wire)
ESBI A3 CAD drawing showing 110kV Braced Wood Pole Set elevation and plan view at 1:100
Meath needs new power supply to meet growing demand 01 October 2008
EIRGRID met elected members of Meath County Council to update them on the two transmission projects planned for the north east.
Cigr� Survey of 380kV to 500kV Overhead Transmission Line Projects Summary Report
The following report details the findings of an ESB International (ESBI) survey
conducted to obtain information on projects relating to electrical infrastructure
within CIGR� member Countries. An email questionnaire was issued to the
members of Working Group B2 06 �Principles of Overhead Line Design� and
also to members of Study Committee B2. The survey requested information
on Overhead Lines in the voltage range 380kV to 500kV that are currently in
planning, construction or commissioned since the year 2000.