ECP-2.2 TSO Category A Batch
ECP-2.2 Category A Update to include nodal assignment,
planning permission details and offer issuance quarters.
2021-Batch-(ECP-2.2)-Results-TSO-Publication_May-2022_Final.pdf
2020 Batch (ECP-2.1) Results - Joint SO Publication_April 2022_Final
Report detailing the outcome of ECP-2.1 and status of projects
processed.
2020-Batch-(ECP-2.1)-Results-Joint-SO-Publication_April-2022_Final.pdf
Q1 2022 ATR Status Update - published 29-April-22
The document provides a quarterly update on ATR completion or
scheduled completion dates, so that generators can track the
status of the ATRs associated with their generation
project(s).
2022-Q1-ATR-Status-Update-FINAL.pdf
EirGrid and SONI Balancing Market Principles Statement V5.1
BMPS V5.1 – External Consultation of proposed BMPS updates for 2022.
EirGrid-and-SONI-Balancing-Market-Principles-Statement-V5.1.pdf
Balancing Market Principles Statement - Cover Note V5.1
Balancing-Market-Principles-Statement-Cover-Note-V5.1.pdf
EirGrid Ex-Post Outturn Availability Connection Asset Maintenance Report 2021
Review of OACA maintenance work carried out in 2021
EirGrid-Ex-Post-Outturn-Availability-Connection-Asset-Maintenance-Report-2021.pdf
EirGrid Ex-Post Outturn Availability Connection Asset Maintenance Report 2021 - Part 2
Review of OACA maintenance work carried out in 2021
EirGrid-Ex-Post-Outturn-Availability-Connection-Asset-Maintenance-Report-2021-Part-2.xlsx
Contracted TSO Wind Farms as of 31 March 2022
Updated report, re connected projects
TSO-Wind-Contracted-31.03.2022.pdf
Contracted TSO (Non-Wind) Generators as of 31 March 2022
Updated report, re connected projects
TSO-NonWind-Contracted-31.03.2022.pdf
EirGrid Ex-Ante OACA Maintenance Report 2022
Plan for outturn available connection asset maintenance works
in 2022
EirGrid-Ex-Ante-Outturn-Availability-Connection-Asset-Maintenance-Report-2022.pdf