Investment Planning and Delivery Report 2020
This report has been compiled to provide stakeholders with an overview of the transmission development programme as at the end of calendar year 2020, the final year of the Price Control 4 (2016-2020) period; and highlight how each of the six steps works, by reference to 2020 projects.
CP1209 Proposed Replacement of Circuit Breakers AAS
The document sets out EirGrid’s Appropriate Assessment
Screening determination as to whether the project is likely to
significantly affect European sites designated by the EU
Habitats Directive.
CP1197 AEG Circuit Breaker Replacement AAS Determination
The document sets out EirGrid’s Appropriate Assessment
Screening determination as to whether the project is likely to
significantly affect European sites designated by the EU
Habitats Directive.
CP1153 Oldstreet Tynagh Cashla AAS Determination
The document sets out EirGrid’s Appropriate Assessment
Screening determination as to whether the project is likely to
significantly affect European sites designated by the EU
Habitats Directive.
CP1152 Arva protection Upgrade AAS Determination
The document sets out EirGrid’s Appropriate Assessment
Screening determination as to whether the project is likely to
significantly affect European sites designated by the EU
Habitats Directive.
CP1149 Newbridge Cushaling 110kV line Stations Bay Conductors and Lead in Conductor Uprate
The document sets out EirGrid’s Appropriate Assessment
Screening determination as to whether the project is likely to
significantly affect European sites designated by the EU
Habitats Directive.
CP1114 Drybridge and Platin AAS Determination
The document sets out EirGrid’s Appropriate Assessment
Screening determination as to whether the project is likely to
significantly affect European sites designated by the EU
Habitats Directive.
CP1032 Cashla 220kV Station Circuit Breaker Replacement AAS Determination
The document sets out EirGrid’s Appropriate Assessment
Screening determination as to whether the project is likely to
significantly affect European sites designated by the EU
Habitats Directive.
CP1031 Flagford 220kV Station Circuit Breaker Replacement AAS Determination
The document sets out EirGrid’s Appropriate Assessment
Screening determination as to whether the project is likely to
significantly affect European sites designated by the EU
Habitats Directive.
Transmission Development Plan 2020-2029 Consultation Report
The Consultation Report describes the TDP consultation
process. It also provides an overview of the submissions
received and our responses to the issues raised.