Transmission Outage Summary 2023 (Week 15-16)
Fortnightly report of transmission outages scheduled in weeks 15-16
Top-Issue-Weeks-15-16-(20230329).xlsx
Enduring Connection Policy - 2.3 (ECP-2.3) 2022 Category A Initial Batch
This report contains the final list of applicants that will be processed under Category A as part of the 2022 ECP-2.3 batch following payment of the balance of application fees to the relevant SO.
2022-Batch-(ECP-2.3)-Results-Joint-SO-Publication_April-2023_Final.pdf
Transmission Outage Summary 2023 (Week 13-14)
Fortnightly report of transmission outages scheduled in weeks
13-14
Transmission-Outage-Summary-2023-(Week-13-14).xlsx
EirGrid-Ex-Ante Outturn Availability Connection Asset Maintenance Report 2023
Plan for outturn available connection asset maintenance works in
2023
EirGrid-Ex-Ante-Outturn-Availability-Connection-Asset-Maintenance-Report-2023.pdf
EirGrid Ex-Post Outturn Availability Connection Asset Maintenance Report 2022
Review of OACA maintenance work carried out in 2022
EirGrid-Ex-Post-Outturn-Availabilty-Connecttion-Asset-Maintenance-Report-2022.pdf
EirGrid Ex-Post Outturn Availability Connection Asset Maintenance Report 2022 Part 2
Review of OACA maintenance work carried out in 2022
EirGrid-Ex-Post-Outturn-Availability-Connection-Asset-Maintenance-Report-2022-Part-2.xlsx
TSO Imperfections and Constraints Multi-Year Plan 2023-2027
TSO-Imperfections-and-Constraints-multi-year-plan-2023-2027-Consultation.pdf
TSO PR5 Local/Dublin Security of Supply PR5 Balanced Scorecard and Incentive Multi-Year Plan 2023-2027 for public consultation
SoS-Multi-year-plan-2023-2027-FINAL.pdf
TSO Strategic Objectives Multi-Year Plan 2023-2027 Consultation
TSO-Strategic-Objectives-Multi-Year-Plan-2023-2027-Consultation.pdf
ECP 2.2 Solar and Wind Constraints Report - Node Results in Excel Format
ECP 2.2 Constraints Analysis Area Reports
ECP-2.2-constraint-forecast-formatted-results.xlsx